Back to projects

Heritage Park Natural Resources

Calgary, Alberta

completeCultureCCRIS
Federal contribution
$1.6M
$1,577,280
Federal share40%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2019
20202021
Built
Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Heritage Park Society
Construction start
Jan 1, 2020(actual)
Construction end
Sep 16, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Sep 1, 2019
  • Construction end11 months earlyforecast Sep 1, 2022

Also in Calgary

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54403 in the federal list. How to read these figures.