Vivo Expansion
Federal contribution
$15.0M
$15,000,000
Federal share31%
of $49.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
2020202120222023
Built
Approved 2 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Nose Creek Sports and Recreation Association o/a Vivo
- Construction start
- Apr 13, 2021(actual)
- Construction end
- Oct 17, 2023(actual)
Against the original forecast
- Construction start5 weeks lateforecast Mar 8, 2021
- Construction end3 months lateforecast Jul 10, 2023
Also in Calgary
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54407 in the federal list. How to read these figures.