Queen Elizabeth Park Paving Pathways
Charlottetown, Prince Edward Island
Federal contribution
$87,735
Federal share40%
of $220.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
2020
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Charlottetown
- Construction start
- Aug 11, 2020(actual)
- Construction end
- Sep 27, 2020(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2020
- Construction end4 weeks lateforecast Aug 30, 2020