Back to projects

Wrights Creek Bridge Renewal

Charlottetown, Prince Edward Island

completeRecreationCCRIS
Federal contribution
$528,000
Federal share40%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 27, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Charlottetown
Construction start
Jun 15, 2021(actual)
Construction end
Dec 22, 2021(actual)

Against the original forecast

  • Construction end6 months earlyforecast Jun 30, 2022