Back to projects

Environmental Industrial Services Inc. (EISI) - Brudenell Wastewater Treatment System Upgrades

Brudenell, Prince Edward Island

approvedWastewaterGIS
Federal contribution
$650,000
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2019
today
2020202220242026
BuiltForecast

Approved 2 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 25, 2026(forecast)
Construction end
Dec 7, 2026(forecast)

Also in Brudenell