Back to projects

Brudenell Three Rivers Extension 2023

Brudenell, Prince Edward Island

completeDrinking WaterGIS
Federal contribution
$2.4M
$2,387,176
Federal share40%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 30, 2022
ApprovedJan 12, 2023
202320242025
Built

Approved 7 months after the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Three Rivers
Construction start
Jan 6, 2024(actual)
Construction end
Jan 7, 2025(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Dec 15, 2024

Also in Brudenell

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66685 in the federal list. How to read these figures.