Slemon Park - Wastewater Treatment Plant - Head Works

Slemon Park, Prince Edward Island

underwayWastewaterGIS
Federal contribution
$521,540
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 5, 2019
today
20202022202420262028
BuiltForecast

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Slemon Park
Construction start
Aug 5, 2024(actual)
Construction end
Mar 31, 2028(forecast)