Hangar 8 Lift-Station Rehabilitation
Slemon Park, Prince Edward Island
Federal contribution
$264,996
Federal share49%
of $538.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Slemon Park
- Construction start
- Dec 5, 2016(actual)
- Construction end
- Jul 15, 2018(actual)
Against the original forecast
- Construction end11 months lateforecast Aug 18, 2017
Also in Slemon Park
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47148 in the federal list. How to read these figures.