Stratford - Water Station Upgrades - Pondside, Cable Heights, Fullertons, Beacon Hill
Stratford, Prince Edward Island
Federal contribution
$110,957
Federal share40%
of $277.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2019
20202021
Built
Approved 2 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Stratford
- Construction start
- Apr 15, 2021(actual)
- Construction end
- Jul 15, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Dec 7, 2020
- Construction end6 weeks lateforecast Jun 1, 2021
Also in Stratford