Back to projects

Stratford - Pondside Park Multi-Use Courts

Stratford, Prince Edward Island

completeRecreationCCRIS
Federal contribution
$28,696
Federal share40%

of $71.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2019
2020
Built

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Stratford
Construction start
May 13, 2020(actual)
Construction end
Jul 31, 2020(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Aug 31, 2020

Also in Stratford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54468 in the federal list. How to read these figures.