Back to projects

Stratford - Fullerton's Creek Conservation Area Natural Playground

Stratford, Prince Edward Island

completeRecreationCCRIS
Federal contribution
$91,826
Federal share40%

of $229.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2019
20202021
Built

Approved 2 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Stratford
Construction start
Jun 1, 2020(actual)
Construction end
Aug 25, 2021(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 15, 2020
  • Construction end4 weeks lateforecast Jul 31, 2021

Also in Stratford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54469 in the federal list. How to read these figures.