Stratford - Fullerton's Creek Conservation Area Natural Playground
Stratford, Prince Edward Island
Federal contribution
$91,826
Federal share40%
of $229.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2019
20202021
Built
Approved 2 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Stratford
- Construction start
- Jun 1, 2020(actual)
- Construction end
- Aug 25, 2021(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 15, 2020
- Construction end4 weeks lateforecast Jul 31, 2021
Also in Stratford