Back to projects

Kensington Lagoon Upgrades

Kensington, Prince Edward Island

completeWastewaterGIS
Federal contribution
$202,093
Federal share38%

of $530.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 19, 2019
20202021
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Kensington
Construction start
Jul 15, 2020(actual)
Construction end
Oct 1, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast May 4, 2020
  • Construction end10 months lateforecast Dec 1, 2020

Also in Kensington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54492 in the federal list. How to read these figures.