Back to projects

Kensington Credit Union Centre Upgrades

Kensington, Prince Edward Island

completeSportCCRIS
Federal contribution
$843,923
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 18, 2022
20232024
Built

Approved 3 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Kensington
Construction start
May 15, 2023(actual)
Construction end
Oct 31, 2024(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 1, 2022
  • Construction end10 months lateforecast Dec 29, 2023

Also in Kensington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65332 in the federal list. How to read these figures.