Kensington Credit Union Centre Upgrades
Kensington, Prince Edward Island
Federal contribution
$843,923
Federal share40%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 18, 2022
20232024
Built
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Kensington
- Construction start
- May 15, 2023(actual)
- Construction end
- Oct 31, 2024(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 1, 2022
- Construction end10 months lateforecast Dec 29, 2023
Also in Kensington