Town of Kerrobert Watermain Replacement
Federal contribution
$2.5M
$2,477,438
Federal share40%
of $6.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2019
202020212022
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Kerrobert
- Construction start
- Jun 14, 2021(actual)
- Construction end
- Oct 31, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 3, 2021
- Construction end5 months earlyforecast Mar 31, 2023
Also in Kerrobert
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54497 in the federal list. How to read these figures.