Enhancing Interpretive Nature Trail in Kerrobert, Saskatchewan

Kerrobert, Saskatchewan

completeActive TransportationATF
Federal contribution
$30,000
Federal share54%

of $55.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2022
2023
Built

Approved 5 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Kerrobert
Construction start
Sep 21, 2023(actual)
Construction end
Oct 2, 2023(actual)

Against the original forecast

  • Construction start13 months lateforecast Aug 31, 2022
  • Construction end8 weeks earlyforecast Nov 30, 2023

Also in Kerrobert

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64140 in the federal list. How to read these figures.