Town of Outlook Landfill Decommissioning
Federal contribution
$400,000
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2019
20202021202220232024
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Outlook
- Construction start
- Aug 1, 2023(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start23 months lateforecast Aug 26, 2021
Also in Outlook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54517 in the federal list. How to read these figures.