Town of Outlook Landfill Decommissioning

Outlook, Saskatchewan

completeSolid Waste ManagementGIS
Federal contribution
$400,000
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2019
20202021202220232024
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Outlook
Construction start
Aug 1, 2023(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start23 months lateforecast Aug 26, 2021