Town of Outlook Raw Water Intake and Water Treatment Plant Upgrades
Federal contribution
$2.9M
$2,942,984
Federal share40%
of $7.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2021
202120222023202420252026
BuiltForecast
Approved 10 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Outlook
- Construction start
- Oct 3, 2023(actual)
- Construction end
- Mar 31, 2026(forecast)
Also in Outlook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57179 in the federal list. How to read these figures.