The Globe Theatre Revitalization of a Regina Heritage Building, the Prince Edward Building
Federal contribution
$10.8M
$10,831,697
Federal share40%
of $27.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2019
202020212022202320242025
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- The Globe Theater
- Construction start
- Nov 1, 2020(actual)
- Construction end
- Aug 13, 2025(actual)
Against the original forecast
- Construction end8 months earlyforecast Mar 31, 2026
Also in Regina