Roadway Construction between the Nipissing First Nation communities of Yellek and Duchesnay
Nipissing First Nation, Ontario
Federal contribution
$3.3M
$3,308,714
Federal share75%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2019
2020202220242026
BuiltForecast
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Nipissing First Nation
- Construction start
- Nov 24, 2021(actual)
- Construction end
- Jun 5, 2026(forecast)
Against the original forecast
- Construction start7 weeks lateforecast Oct 8, 2021
Also in Nipissing First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54562 in the federal list. How to read these figures.