Water and Wastewater Repairs to Supervisory Control and Data Acquisition systems
Nipissing First Nation, Ontario
Federal contribution
$91,094
Federal share49%
of $184.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
2018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Nipissing First Nation
- Construction start
- Oct 5, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2017
- Construction end10 months lateforecast Jun 1, 2017
Also in Nipissing First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51387 in the federal list. How to read these figures.