Upgrade of the Windigo Island Docking Infrastructure Accessibility
Animakee Wa Zhing #37 First Nation, Ontario
Federal contribution
$207,076
Federal share75%
of $276.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2019
202020212022202320242025
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Animakee Wa Zhing #37
- Construction start
- Oct 31, 2023(actual)
- Construction end
- May 31, 2025(actual)
Against the original forecast
- Construction end13 months lateforecast Apr 30, 2024