Class 4 Septic System Replacements (tank and field) for 5 homes

Animakee Wa Zhing #37 First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$57,884
Federal share49%

of $117.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Animakee Wa Zhing #37
Construction start
Jun 11, 2018(actual)
Construction end
Aug 13, 2018(actual)

Against the original forecast

  • Construction start12 months lateforecast Jun 5, 2017
  • Construction end11 months lateforecast Aug 31, 2017