Refurbishment of the Hornepayne Airport Runway and Terminal

Hornepayne, Ontario

completeRegional And Local AirportsRNIS
Federal contribution
$2.9M
$2,907,908
Federal share62%

of $4.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2020
20212022202320242025
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Township of Hornepayne
Construction start
May 3, 2022(actual)
Construction end
Jul 18, 2025(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Jun 13, 2022
  • Construction end3 weeks lateforecast Jun 30, 2025