Front Street Community Park Upgrade and Expansion
Federal contribution
$78,083
Federal share80%
of $97.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
2022202320242025
Built
Approved 7 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Hornepayne
- Construction start
- Sep 23, 2021(actual)
- Construction end
- Dec 20, 2024(actual)
Also in Hornepayne
- Refurbishment of the Hornepayne Airport Runway and Terminal$2.9M
- Hornepayne Drinking Water Distribution System Upgrades$2.0M
- Community Centre- Upgrading and Expansion of current Facility$1.9M
- Replace 15 Main Valves Within the Water Distribution System$100.0K
- Repair/Replace 20 Curb Stops Within the Water Distribution System$32.9K