Pickle Lake Road Reconstruction
Federal contribution
$1.9M
$1,878,750
Federal share60%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2020
202120222023
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Pickle Lake
- Construction start
- Jul 1, 2021(actual)
- Construction end
- Oct 20, 2023(actual)
Against the original forecast
- Construction end14 months earlyforecast Dec 31, 2024
Also in Pickle Lake
- Safe Drinking Water Tower Rehabilitation$80.0K
- Sewage Clarifier Rehabilitation, Tank Rake-Paddle Installation (Cat Lake Road)$44.3K
- Broken hydrant replacement near 1 Koval Street and upgrading approximately 30 metres of water main to prevent future freeze-ups.$4.9K
- Township of Pickle Lake Asset Management$3.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54625 in the federal list. How to read these figures.