Broken hydrant replacement near 1 Koval Street and upgrading approximately 30 metres of water main to prevent future freeze-ups.
Federal contribution
$4,865
Federal share13%
of $38.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Pickle Lake
- Construction start
- May 27, 2019(actual)
- Construction end
- Oct 1, 2019(actual)
Against the original forecast
- Construction start2.1 years lateforecast May 6, 2017
Also in Pickle Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49647 in the federal list. How to read these figures.