2019 Expansion Conventional Bus

Stratford, Ontario

completePublic TransitPTIS
Federal contribution
$228,000
Federal share40%

of $570.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 26, 2020
2021
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Stratford
Construction start
Jul 1, 2020(actual)
Construction end
Feb 6, 2021(actual)

Against the original forecast

  • Construction start4 months earlyforecast Oct 30, 2020
  • Construction end7 weeks earlyforecast Mar 30, 2021