City of Toronto 2020/2021 Culvert Rehabilitation
Federal contribution
$8.7M
$8,738,800
Federal share40%
of $21.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
2020202120222023
Built
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jul 28, 2020(actual)
- Construction end
- Sep 23, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 2, 2020
- Construction end9 months lateforecast Dec 31, 2022