Back to projects

Conventional Bus Refurbishment

Peterborough, Ontario

completePublic TransitPTIS
Federal contribution
$620,000
Federal share50%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 24, 2020
202020212022
Built

Approved 5 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Peterborough
Construction start
Jan 31, 2020(actual)
Construction end
Mar 25, 2022(actual)

Also in Peterborough

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54673 in the federal list. How to read these figures.