Conventional Bus Refurbishment
Federal contribution
$620,000
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 24, 2020
202020212022
Built
Approved 5 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Peterborough
- Construction start
- Jan 31, 2020(actual)
- Construction end
- Mar 25, 2022(actual)
Also in Peterborough
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54673 in the federal list. How to read these figures.