TCAP Dehumidification, Air Exchange Replacement and Insulation
Montague, Prince Edward Island
Federal contribution
$170,695
Federal share34%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
2020202120222023
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- TCAP Co-operative Limited
- Construction start
- Dec 31, 2019(actual)
- Construction end
- Mar 15, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Dec 1, 2019
- Construction end2 weeks earlyforecast Mar 31, 2023
Also in Montague