Specialized Van Replacement
Federal contribution
$237,079
Federal share40%
of $592.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 24, 2020
2021
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Peterborough
- Construction start
- Mar 25, 2020(actual)
- Construction end
- Jul 5, 2021(actual)