Back to projects

2020 Replacement Buses (2)

Stratford, Ontario

completePublic TransitPTIS
Federal contribution
$456,001
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 26, 2020
2021
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Stratford
Construction start
Jul 1, 2020(actual)
Construction end
Feb 6, 2021(actual)

Against the original forecast

  • Construction start3 months earlyforecast Oct 15, 2020
  • Construction end8 weeks earlyforecast Mar 31, 2021

Also in Stratford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55060 in the federal list. How to read these figures.