2019 Road Rehabilitation V - Grand Marais Road - Dougall Avenue to Dominion Boulevard
Federal contribution
$76,967
Federal share40%
of $192.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Windsor
- Construction start
- Jul 16, 2020(actual)
- Construction end
- Apr 1, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2020
- Construction end3 months lateforecast Dec 31, 2021