Transit Terminal Rehabilitation
Federal contribution
$249,928
Federal share40%
of $624.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2020
today
2021202320252027
BuiltForecast
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of North Bay
- Construction start
- Dec 1, 2020(actual)
- Construction end
- Dec 31, 2026(forecast)
Also in North Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55114 in the federal list. How to read these figures.