Improvements to Specialized Transit Buses (Installation of Automated Vehicle Location System and Security Cameras)
Federal contribution
$30,447
Federal share40%
of $76.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2020
20212022202320242025
Built
Approved 5 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of North Bay
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Dec 31, 2024(actual)
Also in North Bay