2020 Fare Box System
Federal contribution
$60,306
Federal share40%
of $150.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 26, 2020
2021
Built
Approved 2 weeks after the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Stratford
- Construction start
- Jul 15, 2020(actual)
- Construction end
- Feb 6, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2020
- Construction end6 months lateforecast Jul 31, 2020
Also in Stratford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55128 in the federal list. How to read these figures.