Cabana Corridor Improvements Phase 3 & 4 - Cabana Road West from Dougall Avenue to Rankin Avenue
Federal contribution
$939,915
Federal share40%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2020
2021202220232024
Built
Approved 8 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Windsor
- Construction start
- May 11, 2020(actual)
- Construction end
- Feb 16, 2024(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Mar 31, 2024
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55133 in the federal list. How to read these figures.