Cabana Corridor Improvements Phase 3 & 4 - Cabana Road West from Dougall Avenue to Rankin Avenue

Windsor, Ontario

completeActive TransportationPTIS
Federal contribution
$939,915
Federal share40%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2020
2021202220232024
Built

Approved 8 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Windsor
Construction start
May 11, 2020(actual)
Construction end
Feb 16, 2024(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast Mar 31, 2024

Also in Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55133 in the federal list. How to read these figures.