2021 Accessible Stops with Shelters

Stratford, Ontario

completePublic TransitPTIS
Federal contribution
$55,933
Federal share40%

of $139.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 18, 2020
2021
Built

Approved 6 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Stratford
Construction start
Aug 28, 2021(actual)
Construction end
Oct 15, 2021(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Oct 1, 2021

Also in Stratford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55149 in the federal list. How to read these figures.