North East Industrial Park Active Transportation and Transit Shelters
Federal contribution
$1.3M
$1,320,000
Federal share40%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2020
202020212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Belleville
- Construction start
- Aug 1, 2020(actual)
- Construction end
- Sep 15, 2025(actual)
Against the original forecast
- Construction end4 months earlyforecast Dec 31, 2025
Also in Belleville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55155 in the federal list. How to read these figures.