Back to projects

North East Industrial Park Active Transportation and Transit Shelters

Belleville, Ontario

completeActive TransportationPTIS
Federal contribution
$1.3M
$1,320,000
Federal share40%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2020
202020212022202320242025
Built

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Belleville
Construction start
Aug 1, 2020(actual)
Construction end
Sep 15, 2025(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2025