Back to projects

Cycling network Expansion and Enhancements

Guelph, Ontario

underwayActive TransportationPTIS
Federal contribution
$1.9M
$1,863,268
Federal share17%

of $11.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2020
today
20202023202620292032
BuiltForecast

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Sep 23, 2021(actual)
Construction end
Oct 1, 2033(forecast)

Also in Guelph

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55163 in the federal list. How to read these figures.