New Bus Shelters, Concrete Pads and Digital Signage at Bus Stops
Federal contribution
$176,400
Federal share40%
of $441.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2020
today
20202022202420262028
BuiltForecast
Approved 6 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of North Bay
- Construction start
- Feb 1, 2021(actual)
- Construction end
- Dec 31, 2027(forecast)
Also in North Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55174 in the federal list. How to read these figures.