Back to projects

New Bus Shelters, Concrete Pads and Digital Signage at Bus Stops

North Bay, Ontario

underwayPublic TransitPTIS
Federal contribution
$176,400
Federal share40%

of $441.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 28, 2020
today
20202022202420262028
BuiltForecast

Approved 6 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of North Bay
Construction start
Feb 1, 2021(actual)
Construction end
Dec 31, 2027(forecast)

Also in North Bay