Back to projects

Sidewalk Construction and Stormwater Improvements

North Bay, Ontario

underwayPublic TransitPTIS
Federal contribution
$3.6M
$3,559,534
Federal share40%

of $8.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 28, 2020
today
2021202320252027
BuiltForecast

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of North Bay
Construction start
May 21, 2020(actual)
Construction end
Dec 31, 2026(forecast)

Also in North Bay