Sidewalk Construction and Stormwater Improvements
Federal contribution
$3.6M
$3,559,534
Federal share40%
of $8.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2020
today
2021202320252027
BuiltForecast
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of North Bay
- Construction start
- May 21, 2020(actual)
- Construction end
- Dec 31, 2026(forecast)
Also in North Bay