Fleet Garage and Bus Barn Upgrades: Central Vacuum System and Garage Doors
Federal contribution
$60,384
Federal share50%
of $120.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2020
20212022
Built
Approved 5 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of North Bay
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Jun 30, 2022(actual)
Also in North Bay