Transit Priority Investments with Major Stations

Greater Sudbury, Ontario

approvedPublic TransitPTIS
Federal contribution
$6.4M
$6,375,000
Federal share40%

of $15.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2020
today
20212023202520272029
BuiltForecast

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Greater Sudbury
Construction start
Apr 1, 2026(forecast)
Construction end
Mar 30, 2029(forecast)

Also in Greater Sudbury