Transit Route Access Improvements
Federal contribution
$793,320
Federal share40%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2020
202120222023
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Windsor
- Construction start
- Jun 22, 2020(actual)
- Construction end
- Jun 2, 2023(actual)
Against the original forecast
- Construction end7 months earlyforecast Dec 31, 2023
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55205 in the federal list. How to read these figures.