2021 Replacement Buses (2)
Federal contribution
$456,001
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 26, 2020
20212022
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Stratford
- Construction start
- Sep 2, 2021(actual)
- Construction end
- Mar 9, 2022(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Apr 1, 2022
Also in Stratford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55213 in the federal list. How to read these figures.