Tobique First Nation - Main Street Road Restoration
Tobique Narrows, New Brunswick
Federal contribution
$936,232
Federal share75%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2021
2021
Built
Approved 16 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Tobique First Nation
- Construction start
- Jun 1, 2020(actual)
- Construction end
- May 31, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2020
- Construction end2 months lateforecast Mar 16, 2021