Neqotkuk - Sidewalk Addition
Tobique Narrows, New Brunswick
Federal contribution
$25,148
Federal share100%
of $25.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
20242025
Built
Approved 19 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Tobique First Nation
- Construction start
- Aug 15, 2024(actual)
- Construction end
- Nov 20, 2024(actual)
Against the original forecast
- Construction start11 months lateforecast Sep 1, 2023
- Construction end11 months lateforecast Dec 31, 2023
Also in Tobique Narrows
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 68101 in the federal list. How to read these figures.