Water Systems Upgrades
Federal contribution
$54,136
Federal share40%
of $135.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 12, 2020
2021
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Justin
- Construction start
- May 1, 2021(actual)
- Construction end
- Nov 1, 2021(actual)
Against the original forecast
- Construction start6 months earlyforecast Nov 1, 2021
- Construction end6 months earlyforecast May 10, 2022
Also in Saint-Justin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56286 in the federal list. How to read these figures.