Renewal of water pipes
Federal contribution
$209,927
Federal share50%
of $419.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 27, 2017
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Saint-Justin
- Construction start
- Nov 28, 2017(actual)
- Construction end
- Jul 16, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast May 15, 2017
- Construction end8 months earlyforecast Mar 31, 2019
Also in Saint-Justin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48874 in the federal list. How to read these figures.